Parsons KS WWTP Expansion

PROJECT TIMING: 
Summer 2004 Start Const
Startup  August 23, 2005

Construction Bid:  $4.3 million by LaForge & Budd
Engineering Costs approx:  $400,000

CONSTRUCTION BID/GALLON$1.76

PROJECT EQUIPMENT SUPPLIED

3       50 HP VFD Submersible Pumps in existing vault - will reduce O&M by $10,000+ per year
     Each pump will pump 2,800 gpm to the headworks
1       Schreiber Fine 6 mm Opening Step Screen for 12 MGD with washer compactor
1EnviroDyne Systems Incl Vortex Grit Chamber for 12 MGD
2Schreiber GR Treatment Trains with DO control for Optimized oxygen control and energy savings
6Kaeser 30 HP PD Blowers with Acoustical enclosures indoors
24 MGD each clarifiers with scum pumping
1WEDECO UV channel with two channels and self cleaning wipers
2Flow meters for Effluent and bypass flow monitoring as required by KDHE
2Floating aerators for sludge holding tanks
1SCADA system with fiberoptic cables between all I/O panels
1Process warranty for effluent performance
1Filters can be added when permit requires by KDHE
1Reuse the existing trickling filter plant for storm water holding and treatment for excess flows
50 Year Old Trickling filter taken out of service
Rotating Bridge with diffusers operational
Panelview Plus illustration on aeration basins
HEADWORKS BUILDING
6 mm Opening Screen with Washer Compactor
Vortex Grit Chamber
Influent VFD Pump Station
Peak Flow Peakflow bypass actuated gate
Schreiber Fine Screen -
Schreiber Washer/Compactor
EnviroDyne Vortex Grit Chamber
Grit Chamber Classifier discharge
Panelview Plus Control Screens
RAS PUMPING AND CONTROLS
BLOWER GALLERY
EFFLUENT WATER QUALITY AND CASCADE AERATION
MCC ROOM AND SCADA SYSTEM CONTROLS
REMOTE PANELS FOR LOCAL I/O
  Analog and Digital inputs

Located as follows:

CP-2   Lower level in main building
CP-3   Sludge Digestion Area
CP-4   Influent Lift Station Area
New Plant in "background" with old trickling filter plant used as peak flow basin design and aerobic sludge digestion
WEDECO UV Disinfection -
SELF CLEANING LAMP SLEEVES
Blue Panels     -    Ballast Enclosures
Channel:  -     Two channels with two banks/channel
Gates:    -     Each channel has control gate